Private Property Inflow & Infiltration Reduction Program In 2022, over 180 letter agreements were compiled into contracts for sewer lateral rehabilitation work to repair broken pipe and to stop leaks. In 2023, this work continues to rehabilitate building sewer laterals from sewer mains. Additional information on this Sewer Lateral… Read More Tamerlane Drive Sanitary Lift Station “O” Parallel Force Main Project In the summer-fall of 2023, the City of Mequon is planning to construct a parallel sanitary force main in County Line Road from Tamerlane Drive to Granville Road. Vehicular Detours are anticipated to allow work shaft construction. Traffic detours are planned to route… Read More Public Information Meeting August 23, 2022 from 6:00 p.m. to 8:00 p.m. City of Mequon Voluntary Building Sewer Lateral Rehabilitation The City of Mequon is hosting another Public Information Meeting for the proposed Building Sewer Lateral rehabilitation work in the Riverdale Park Lift Station ‘F’ area and Riverland Drive Lift Station ‘… Read More East Trunk Sewer Project In response to flooding that resulted from the June 2014 and April 2015 wet weather events that caused numerous basement back-ups, the Sewer Utility District commissioned a study for a wet weather relief sewer. In 2016 the Common Council approved this study, design was completed… Read More Water Main Extension on Buntrock Avenue Betterment of Services As part of the Mequon Water Utility Capital Program Budget and in coordination with the Village of Thiensville, a water main extension in Buntrock Avenue was completed from the Seminary Drive past North Orchard Street to Main Street in Thiensville. This water main extension… Read More Sanitary Sewer Rehabilitation on Cedarburg Road As part of the Mequon Sewer Utility Capital Program Budget and in coordination with the Village of Thiensville, a third phase to rehabilitate the Mequon-Thiensville Sanitary is planned to begin in spring 2021 in Cedarburg Road. This sanitary… Read More Water Main Relocation for I-43 Freeway at Highland Road and Port Washington Road near County Line Road As part of the Wisconsin Department of Transportation I-43 reconstruction project, the Mequon Water Utility is relocating water main along Port Washington Road to avoid impacts of a new sound wall and also at Highland Road for a new bridge with on/off ramps. This utility work is… Read More Parkview Drive Lift Station “B” Back-Up Generator Installation In July 2020, the Sewer Utility District Commission and Common Council authorized installation of a back-up generator for the City’s sanitary lift station pump. This lift station is located along Parkview Drive in the Mequon Country Estates Subdivision near Homestead… Read More County Line Road Sanitary Lift Station “Q” Force Main Replacement In the summer of 2021, the City of Mequon is planning to replace the sanitary force main in County Line Road from Reibs Road to Arrowood Drive. Vehicular Detours are planned after the 4th of July as the road will be closed to through traffic at the… Read More Sanitary Sewer Overflows and Wet Weather Events Wet weather events, such as intense rainfall and/or snowmelts, often cause supersaturated soil conditions which can be attributed to inflow and infiltration of clear water in sanitary sewer collection systems. While the sanitary sewer collection system is designed to accommodate an amount… Read More Riverdale Park and Riverland Drive Infiltration Grouting Project Routine inspection of the sanitary system pipes in the Riverland Drive and Riverdale Park areas revealed numerous joints with infiltration, where groundwater is entering into to the sanitary sewer system. This project will test and grout nearly four miles of pipe joints to prevent further… Read More View PDF of Page
Private Property Inflow & Infiltration Reduction Program In 2022, over 180 letter agreements were compiled into contracts for sewer lateral rehabilitation work to repair broken pipe and to stop leaks. In 2023, this work continues to rehabilitate building sewer laterals from sewer mains. Additional information on this Sewer Lateral… Read More
Tamerlane Drive Sanitary Lift Station “O” Parallel Force Main Project In the summer-fall of 2023, the City of Mequon is planning to construct a parallel sanitary force main in County Line Road from Tamerlane Drive to Granville Road. Vehicular Detours are anticipated to allow work shaft construction. Traffic detours are planned to route… Read More
Public Information Meeting August 23, 2022 from 6:00 p.m. to 8:00 p.m. City of Mequon Voluntary Building Sewer Lateral Rehabilitation The City of Mequon is hosting another Public Information Meeting for the proposed Building Sewer Lateral rehabilitation work in the Riverdale Park Lift Station ‘F’ area and Riverland Drive Lift Station ‘… Read More
East Trunk Sewer Project In response to flooding that resulted from the June 2014 and April 2015 wet weather events that caused numerous basement back-ups, the Sewer Utility District commissioned a study for a wet weather relief sewer. In 2016 the Common Council approved this study, design was completed… Read More
Water Main Extension on Buntrock Avenue Betterment of Services As part of the Mequon Water Utility Capital Program Budget and in coordination with the Village of Thiensville, a water main extension in Buntrock Avenue was completed from the Seminary Drive past North Orchard Street to Main Street in Thiensville. This water main extension… Read More
Sanitary Sewer Rehabilitation on Cedarburg Road As part of the Mequon Sewer Utility Capital Program Budget and in coordination with the Village of Thiensville, a third phase to rehabilitate the Mequon-Thiensville Sanitary is planned to begin in spring 2021 in Cedarburg Road. This sanitary… Read More
Water Main Relocation for I-43 Freeway at Highland Road and Port Washington Road near County Line Road As part of the Wisconsin Department of Transportation I-43 reconstruction project, the Mequon Water Utility is relocating water main along Port Washington Road to avoid impacts of a new sound wall and also at Highland Road for a new bridge with on/off ramps. This utility work is… Read More
Parkview Drive Lift Station “B” Back-Up Generator Installation In July 2020, the Sewer Utility District Commission and Common Council authorized installation of a back-up generator for the City’s sanitary lift station pump. This lift station is located along Parkview Drive in the Mequon Country Estates Subdivision near Homestead… Read More
County Line Road Sanitary Lift Station “Q” Force Main Replacement In the summer of 2021, the City of Mequon is planning to replace the sanitary force main in County Line Road from Reibs Road to Arrowood Drive. Vehicular Detours are planned after the 4th of July as the road will be closed to through traffic at the… Read More
Sanitary Sewer Overflows and Wet Weather Events Wet weather events, such as intense rainfall and/or snowmelts, often cause supersaturated soil conditions which can be attributed to inflow and infiltration of clear water in sanitary sewer collection systems. While the sanitary sewer collection system is designed to accommodate an amount… Read More
Riverdale Park and Riverland Drive Infiltration Grouting Project Routine inspection of the sanitary system pipes in the Riverland Drive and Riverdale Park areas revealed numerous joints with infiltration, where groundwater is entering into to the sanitary sewer system. This project will test and grout nearly four miles of pipe joints to prevent further… Read More